Public Works Yard Updates Project: Options for Next Steps

Carried 24 Feb 2025The vote
Topic: Other Categories: Economic Development, Infrastructure & Public Services 1 recorded vote 24 Feb 2025 Split

What it does

Purpose
To provide Council with options to progress the Public Works Yard Updates project and seek direction to implement Council’s preferred option.
Staff report, page 1
Staff recommendation
That Council direct Staff to proceed with Detailed Design and Costing and allocate $1,800,000 funded by $1,314,000 from the General Asset Management Reserve Fund, $162,000 from the Sewer Operating Reserve, and $324,000 from the Water Operating Reserve to undertake the work. (Option 4 in the report).
Staff report, page 1

Votes

  1. 24 Feb 2025other
    Carried 6–3Split

    That Council direct Staff to proceed with Detailed Design and Costing and allocate $1,800,000 funded by $1,314,000 from the General Asset Management Reserve Fund, $162,000 from the Sewer Operating Reserve, and $324,000 from the Water Operating Reserve to undertake the work. (Option four in the report).

Voted No