BylawNo. 7362

Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362

Abandoned 12 Feb 2024The vote
Topic: Economy Categories: Economic Development, Infrastructure & Public Services, Governance & Civic Engagement 4 recorded votes 19 Jun 2023 to 12 Feb 2024 Split

What it does

Motion
To authorize the borrowing of up to $48,500,000 for the construction of the Nanaimo Operations Centre and the required supporting facilities
The motion, 19 Jun 2023
Purpose
To introduce “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362”, for first, second and third readings.
Staff report, page 1
Staff recommendation
That: 1. “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362” (To authorize the borrowing of up to $48,500,000 for the construction of the Nanaimo Operations Centre and the required supporting facilities), pass first reading; 2. “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362” pass second reading; and. 3. “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362” pass third reading.
Staff report, page 1

Votes

  1. 19 Jun 2023other
    Carried 8–0Absent 1

    That Council: 1. determine the total number of electors of the area to which the approval process applies (the whole of the City of Nanaimo) to be 77,990; 2. establish a deadline of 4:30 p.m. on Friday, 2023- NOV-03 for receiving elector responses for the Alternative Appro val Process in relation to “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362”; and, 3. approve the Elector Response Form as attached to the Staff report dated 2023-JUN-19.

  2. 19 Jun 2023first, second and third reading
    Carried 8–0Absent 1

    It was moved and seconded that "Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362" (To authorize the borrowing of up to $48,500,000 for the construction of the Nanaimo Operations Centre and the required supporting facilities), pass first reading; It was moved and seconded that "Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362" pass second reading; and, It was moved and seconded thatNanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362" pass third reading.

  3. 4 Dec 2023other
    Carried 7–2Split

    That Council move forward with a second Alternative Approval Process in relation to “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362” and: 1. determine the total number of electors of the area to which the approval process applies (the whole of the City of Nanaimo) to be 78,892; 2. establish a deadline of 4:30 p.m. on Tuesday, 2024- FEB-20 for receiving elector responses for the Alternative Approval Process in relation to “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362”; and, 3. approve the Elector Response Form as attached to the Staff report titled “Nanaimo Operations Centre Alternative Approval Process” dated 2023-DEC-04.

  4. 12 Feb 2024abandonment
    Carried 8–0Absent 1

    That Council a. Cancel the current Alternative Approval Process; b. Abandon “Nanaimo Operations Centre Phase One Borrowing Bylaw 2023 No. 7362”; and, c. Direct Staff to return to Council with options to fund Phase One of the Nanaimo Operations Centre project.

Voted No