Decision
Albert and Fourth Street & Utility Upgrade Project
Carried 20 Mar 2023The vote
What it does
Purpose, from an earlier report
To seek Council direction to amend the budget for the Albert and Fourth Street & Utility Upgrade project from $3,763,701 to $4,314,494 in the 2023-2027 Financial Plan.Staff report, page 1
Votes
-
20 Mar 2023otherCarried 9–0
That Council increase the budget for the Albert and Fourth Street & Utility Upgrade project in 2023 from $3,763,701 to $4,367,120 funded by $298,013 from the Water Asset Management Reserve Fund, $289,986 from the BC Active Transportation Grant and $15,420 from Water DCC contingency fund.
Documents
- Staff report, 20 Mar 2023
- Meeting agenda, 20 Mar 2023 Albert and Fourth Street & Utility Upgrade Project