Marie Davidson BMX Park Redevelopment

Carried 22 Apr 2024The vote
Topic: Environment Categories: Economic Development, Parks & Recreation 1 recorded vote 22 Apr 2024

What it does

Purpose, from an earlier report
To update the Finance and Audit Committee on project progress and to request additional funds to complete the Marie Davidson BMX Redevelopment Project (the “Project”).
Staff report, page 1

Votes

  1. 22 Apr 2024other
    Carried 9–0

    That Council increase the 2024 project budget for the Marie Davidson BMX park by $330,000 from $1,507,827 to $1,837,827 and fund the increase from the Growing Communities Fund Reserve.