Decision
Sanitary Sewer Trunk Capacity Constraints (Part 1)
Carried 22 Jun 2026The vote
Votes
-
22 Jun 2026otherCarried 9–0
That Council direct Staff to investigate long term borrowing implications and options to facilitate near term sanitary sewer trunk upgrades and provide a report back to Council.
-
22 Jun 2026otherCarried 9–0
That Council direct Staff to develop an enhanced inflow and infiltration (I&I) reduction program for Council’s consideration.
-
22 Jun 2026otherCarried 9–0
That Council direct Staff to continue permitting new or larger sewer connections where the additional load on the sewer is nominal and the risk is mitigated through planned capacity upgrades.